Former Wollongong Gasworks Remediation

OVERVIEW

The former Wollongong Gasworks was operated by the Wollongong Gas Light Company as a coal gasification plant (gasworks) between 1883 and 1977.

Jemena Gas Networks (NSW) Ltd (Jemena), a subsidiary of Jemena Limited acquired the site following the transaction of assets from the Australian Gas Light Company (AGL) in 2007. Following the acquisition, Jemena became responsible for the site and legacy gasworks contamination.

There have been numerous investigations undertaken at the site between 1997 and 2019. The soil and groundwater at the site have been contaminated by the historical waste and by-products produced during the operation of the gasworks.

The gas manufacturing infrastructure formerly located on the site included a retort house, boiler, exhaust house, washers and purifiers, coal storage areas, tar wells, gas holders and a drum filling area. The aboveground site infrastructure was demolished in the 1980s and a large section of the site (Lot 2412) was remediated by excavation of infrastructure and hydrocarbon impacted soil in 2005.

The NSW Environment Protection Authority (EPA) issued a Section 77 Notice requesting information on the current status of the site; and Jemena submitted a Detailed Site Investigation (DSI) report to the EPA in January 2017. The EPA reported that they would not declare the site contaminated under the CLM Act 1997, based on the understanding that Jemena will continue to progress the remediation in a timely manner, with ongoing regular communication with the EPA.

To ensure the remediation works are completed in accordance with the applicable regulatory requirements Jemena engaged a Site Auditor accredited by the NSW EPA under the Contaminated Land Management Act 1997.

Since the completion of the 2005 remediation works, a number of investigations have been conducted at the site, including works contributing to the removal of stockpiles in December 2018. Following the removal of the stockpiles, Jemena’s environmental consultants Senversa prepared a Remediation Action Plan (RAP) which provides the direction for the emediation works. The RAP has been reviewed by the appointed Site Auditor and was also submitted to the NSW EPA.

Due to the complexities of the project and to ensure minimal disruption to the community, Jemena continues to engage extensively with specialist consultants, contractors and government departments, ensuringthe project is appropriately planned and completed.

The survey is now closed. Thanks for participating.

2021 Project Update

Update on Remediation works - Relocation of the Environmental Control Enclosure has commenced.

  • Engagement of Remediation Contractor

    Remediation contractor, Ventia engaged to undertake the works (Qtr 1, 2020)

  • Complete Site works

    Remediation Works are planned to be completed in Qtr 4, 2021

  • Remediation of the Site complete

    All works are progressing well and planned to be completed by Qtr 4, 2021

  • Remediation Works commence

    Remediation works commenced on Site in Qtr 2, 2020

  • Stockpile Removal Works

    Removal of stockpiles from previous remediation works.

  • Project Management & Community Consultation

    Project Management & Community Consultation

     

  • Demolition & Tree Removal Works

    Demolition of three existing buildings to enable future remediation works on the Property.

Since the 2005 remediation works, a number of investigations have been conducted at the site. A NSW EPA accredited Contaminated Sites Auditor has been engaged to provide technical input and oversight for the project.

Following the completion of last phase of investigations at Wollongong, Environmental Earth Sciences was engaged to undertake a Data Gap Analysis (DGA) and Remediation Options Assessment (ROA). The recommendations from the ROA was used to develop a Remediation Action Plan (RAP). This RAP was reviewed by the NSW EPA accredited Site Auditor and the NSW EPA. Due to the complexities of the project and to ensure minimal disruption to the community, Jemena continues to engage extensively with specialist consultants, contractors and government departments. This ensures the project is appropriately scoped, planned and implemented.